An Appraisal of discrepancies between estimated and final cost in Turkish public work projects: A case study

Devlet ihalelerinde tahmin edilen ve gerçekleşen maliyetler arasındaki tutarsızlıkların değerlendirilmesi

  1. Tez No: 116489
  2. Yazar: MUHSİN TAMER ÖZDEMİR
  3. Danışmanlar: YRD. DOÇ. DR. SOOFİA TAHİRA ELİAS ÖZKAN
  4. Tez Türü: Yüksek Lisans
  5. Konular: Mimarlık, Architecture
  6. Anahtar Kelimeler: Keşif, Nakit Akışı, Hakediş Ödemeleri, Artışı, ilave iş. VI, Cost Estimates, Cash Flow, Progress Payments, Bill of Quantities, Additional Works IV
  7. Yıl: 2001
  8. Dil: İngilizce
  9. Üniversite: Orta Doğu Teknik Üniversitesi
  10. Enstitü: Fen Bilimleri Enstitüsü
  11. Ana Bilim Dalı: Mimarlık Ana Bilim Dalı
  12. Bilim Dalı: Belirtilmemiş.
  13. Sayfa Sayısı: 135

Özet

öz DEVLET İHALELERİNDE TAHMİN EDİLEN VE GERÇEKLEŞEN MALİYETLER ARASINDAKİ TUTARSIZLIKLARIN DEĞERLENDİRİLMESİ ÖZDEMİR, Muhsin Tamer Yüksek Lisans, Mimarlık Bölümü Tez Yöneticisi: Yrd. Doç. Dr. Soofia Tahira Elias ÖZKAN Eylül 2001, 121 sayfa Türkiye'deki inşaat sektörünün önemli bir bölümünü oluşturmasına rağmen, devlet ihalelerinin sadece sınırlı sayıdaki bir bölümü planlanan zamanında tamamlanabilmekte ve daha da az sayıda bölümü de planlanan maliyetler içerisinde gerçekleştirilebilmektedir. Bununla birlikte, projelerin inşaa aşamasında sürekli revizyonlar gerekli olmaktadır. Bu durum, hem devlet, hem tasarımcı, hem de müteahhit açısından bir çok probleme yol açmaktadır. inşaat sektöründe, ileriye dönük tahminler olmalarından dolayı, keşifler ile gerçekleşen maliyetler arasında sapmalar olması kaçınılmazdır. Önemli olan, sözkonusu sapmaların en az seviyede tutulmasını sağlayacak planlama çalışmalarının yapılmasıdır. Bu çalışma, devlet ihalelerinde, keşifler doğrultusunda tahmin edilen nakit akış planları ile gerçekleşen nakit akışı arasındaki tutarsızlıkların değerlendirilmesi üzerine yoğunlaşmaktadır. Sözkonusu tutarsızlık ve farklılıkların sebepleri, yakın zamandatamamlanmış bir devlet yatırımı üzerinde çalışılarak araştırılmış, ve bu farklılıkların oluşmasında rolü olan tarafların etkileri incelenmiştir. Proje aşamasında yapılan keşiflerdeki değişikliklerin kaçınılmaz olacağının ortaya konulmasını müteakip, Microsoft Excel yazılımı kullanılarak bir Lineer Regresyon analizi yapılmış ve keşifler ile gerçek maliyetler arasındaki ilişki incelenmiştir.

Özet (Çeviri)

ABSTRACT AN APPRAISAL OF DISCREPANCIES BETWEEN ESTIMATED AND FINAL COSTS IN TURKISH PUBLIC WORKS PROJECTS: A CASE STUDY ÖZDEMİR, Muhsin Tamer M.Sc. in Building Science, Department of Architecture Supervisor: Soofia Tahira Elias Özkan, Ph.D., Assist. Prof. In the Department of Architecture September 2001, 121 pages Although public construction projects hold a significant position in the construction sector in Turkey, only a small number of them are completed before their deadlines, and an even smaller number are completed within their estimated budgets. Constant revisions are consequently required throughout their execution. This situation creates many problems for both the government and the contractors. The estimates in the construction sector are inevitably subject to error since they are mere predictions. Hence, it is important to make accurate planning studies in order to minimize these changes. The focus of this study was on the appraisal of the discrepancies between the estimated and the actual cash flows of public works in the Turkish construction industry. The probable sources of these discrepancies were investigated by analyzing data gathered from a recent public works investment as a case iiistudy. The roles and the effects of the several parties concerned were also explored. Having determined the fact that changes in estimations inevitably occur, a linear regression analysis was made by using the computer application Microsoft Excel to establish the relationship between estimated and final costs.

Benzer Tezler

  1. İmalat endüstrisinde aktiviteye dayalı maliyetlendirme sistemi ile kalite maliyetlerinin belirlenmesi

    Determining quality costs using activity based costing in a manufacturing company

    BUKET AKKUŞ

    Yüksek Lisans

    Türkçe

    Türkçe

    1997

    Endüstri ve Endüstri Mühendisliğiİstanbul Teknik Üniversitesi

    Endüstri Mühendisliği Ana Bilim Dalı

    DOÇ. DR. SEÇKİN POLAT

  2. Deney tasarımı yöntemlerinin karşılaştırmalı kullanımı ile sert seramik kaplı matkap uçlarının performans değerlendirmesi ve optimizasyonu

    Comparative analysis of design of experiment techniques on the performance evaluation and optimization of hard ceramic coated driil bits

    METİN SAVAŞKAN

    Doktora

    Türkçe

    Türkçe

    2003

    Metalurji Mühendisliğiİstanbul Teknik Üniversitesi

    Metalurji Mühendisliği Ana Bilim Dalı

    PROF. DR. YILMAZ TAPTIK

  3. Kalite maliyetleri

    Başlık çevirisi yok

    ALİ ODABAŞ

    Yüksek Lisans

    Türkçe

    Türkçe

    1993

    Endüstri ve Endüstri Mühendisliğiİstanbul Teknik Üniversitesi

    Endüstri Mühendisliği Ana Bilim Dalı

    PROF. DR. ATAÇ SOYSAL

  4. Kalitenin ekonomik analizi

    Başlık çevirisi yok

    GÖKHAN ERGİNCAN

    Yüksek Lisans

    Türkçe

    Türkçe

    1996

    Endüstri ve Endüstri Mühendisliğiİstanbul Teknik Üniversitesi

    PROF.DR. RAMAZAN EVREN

  5. Kurumsal dayanakları ve finansman yöntemleri bağlamında, konut yenileme uygulamaları; Türkiye için model önerisi

    Housing reconstructi̇on practices from the aspects of legal basis and financing methods; a model analysi̇s for Turkey

    SAİM GÜL

    Yüksek Lisans

    Türkçe

    Türkçe

    2019

    Şehircilik ve Bölge PlanlamaMarmara Üniversitesi

    İstatistik Ana Bilim Dalı

    DR. ÖĞR. ÜYESİ NESLİHAN ÇELİK